Tracking The Status Of Implementation Of Metro Project In Bangalore Independently Since 2009

ID: 1985574583068721152

linkhttps://blrmetrotracker.com/ calendar_today04-11-2025 05:07:58

596 Tweet

2,2K Followers

12 Following

Muthi-ur-Rahman Siddiqui (@ever_pessimist) 's Twitter Profile Photo

Happy Sankranti! The 7th #YellowLine train will be inducted on Jan 15. Mon-Sat peak-hour frequency: 10 mins instead of 13 mins. Sun: 14 mins instead of 15 mins. No change in 1st & last train timings from RV Road/Bommasandra. Bangalore Metro Updates BLR Metro Tracker

Happy Sankranti!

The 7th #YellowLine train will be inducted on Jan 15.

Mon-Sat peak-hour frequency: 10 mins instead of 13 mins.

Sun: 14 mins instead of 15 mins.

No change in 1st & last train timings from RV Road/Bommasandra.

<a href="/WF_Watcher/">Bangalore Metro Updates</a> <a href="/blrmetrotracker/">BLR Metro Tracker</a>
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

As per the owner of the crane agency, one of the outrigger of the crane got cut off & detached from the crane, which resulted in crane toppling near Agara Flyover. Crane was in the process of loading steel portal beam on to the trailer. That steel portal beam was supposed be

As per the owner of the crane agency, one of the outrigger of the crane got cut off &amp; detached from the crane, which resulted in crane toppling near Agara Flyover.

Crane was in the process of loading steel portal beam on to the trailer. That steel portal beam was supposed be
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 14-01-2026 NCC P1: • AP273L Cast • AP317R Being Tied • AP199L : L2 Being Tied • AP242 L1 Tiebeam Launched • Veerannapalya Station P3 L PD To CL Cast • Veerannapalya Station P2 CC Beam Being Tied • AP287R : L2 Being Tied NCC P2: • Kodigehalli Station L6

BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 15-01-2026 NCC P1: • AP250R : L1 Cast • AP282 Support For Topbeam • AP243 L1 Tiebeam Launched • AP244 Support For Midbeam • AP319R Cast • UP-AP328 Being Tied • Kasturinagara Station P4 CL To TL Cast • AP318R Tied • Veerannapalya Station P4 L CL To TL

BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 16-01-2026 NCC P2: • Yelahanka L8-UP-AP604 U Girder Launched • UP-AP343 Rebar Up • UP-AP344 Rebar Up • DN-AP354 Pier Cap Tied • Hebbal Station L2 PD To CL Formwork Assembled • Hebbal Station L4 PD Beam Formwork Assembled #Changelog

Rajesh Kumar Agarwal (@rajesh_agarwalb) 's Twitter Profile Photo

Update on 8th yellow line trainset.spotted 1st coach at mulibagal toll plaza .Spoke to the driver.he confirmed that he will reach hebbagodi by Snday nyt.also rest of d 5 coaches are also behind him .Sharing sme pics here Bangalore Metro Updates BLR Metro Tracker Srinivas Alavilli ನಮ್ಮ ಮೆಟ್ರೋ

Update on 8th yellow line trainset.spotted 1st coach at mulibagal toll plaza .Spoke to the driver.he confirmed that he will reach hebbagodi by Snday nyt.also rest of d 5 coaches are also behind him .Sharing sme pics here <a href="/WF_Watcher/">Bangalore Metro Updates</a> <a href="/blrmetrotracker/">BLR Metro Tracker</a> <a href="/srinualavilli/">Srinivas Alavilli</a> <a href="/OfficialBMRCL/">ನಮ್ಮ ಮೆಟ್ರೋ</a>
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 17-01-2026 SNC: • ORP381-ORP382 I Girder Launched NCC P1: • Horamavu Station P1 1x CC Arms Completed • HBR Station P1 CPC Collar Ring • AP283 L2 Tiebeam Tied NCC P2: • UP-AP604-UP-AP605 U Girder Launched • AP336R Tied • DN-AP337 Cast • DN-AP338 Tied

BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 18-01-2026 NCC P1: • Horamavu Station P1 2x CC Arms Completed • HBR Station P8 CL To TL Tied • AP244 L1 Tiebeam Launched #Changelog

Muthi-ur-Rahman Siddiqui (@ever_pessimist) 's Twitter Profile Photo

All 6 coaches of the 8th #YellowLine train reached the Hebbagodi depot this morning. After undergoing the requisite tests, the train will enter passenger ops by mid-Feb. Peak-hr frequency will improve to 8 mins. 1st-train start timings may advance. Bangalore Metro Updates BLR Metro Tracker

All 6 coaches of the 8th #YellowLine train reached the Hebbagodi depot this morning.

After undergoing the requisite tests, the train will enter passenger ops by mid-Feb.

Peak-hr frequency will improve to 8 mins. 1st-train start timings may advance.

<a href="/WF_Watcher/">Bangalore Metro Updates</a>
<a href="/blrmetrotracker/">BLR Metro Tracker</a>
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 19-01-2026 NCC P1: • AP49 Pier Cap Collar Ring Fixed • AP316R Being Tied • AP315R Being Tied • AP287R : L2 Tied • AP241 L1 Tiebeam Launched • AP317R Formwork Assembled NCC P2: • UP-AP354 Being Tied • DN-AP354 Pier Cap Cast NCC P3: • AP906-AP907 LHS U

BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

✨📢 Milestone Update: SNC completes launching all Precast I-Girders & RCC Girders on the viaduct portion of the ORR Metro Project in Phase 2A Package 2 - Between Devarabeesanahalli to Baiyappanahalli. Final I-Girders were launched between the span ORP380-ORP381 at Marathahalli

✨📢 Milestone Update:

SNC completes launching all Precast I-Girders &amp; RCC Girders on the viaduct portion of the ORR Metro Project in Phase 2A Package 2 - Between Devarabeesanahalli to Baiyappanahalli.

Final I-Girders were launched between the span ORP380-ORP381 at Marathahalli
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Success is measured by how we handle challenges. Following the recent incident, the team bounced back strongly 💪 and successfully completed the launch of the steel portal beam at ORP165 near Ibbaluru today. This site is at the Phase 2A (Blue Line) & Phase 3A (Red Line)

Success is measured by how we handle challenges. Following the recent incident, the team bounced back strongly 💪 and successfully completed the launch of the steel portal beam at ORP165 near Ibbaluru today. 

This site is at the Phase 2A (Blue Line) &amp; Phase 3A (Red Line)
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

View of the final I-Girder being launched in ORR Metro Package 2 by SNC, BMRCL & Gandhi Cranes team. A total of 93 spans of I-Girders & RCC girders were present in the scope. Launching & Casting of all of which have now been completed. What follows next is stitching & casting

View of the final I-Girder being launched in ORR Metro Package 2 by SNC, BMRCL &amp; Gandhi Cranes team.

A total of 93 spans of I-Girders &amp; RCC girders were present in the scope. Launching &amp; Casting of all of which have now been completed.

What follows next is stitching &amp; casting
BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 20-01-2026 Afcons: • ORP165 Portal Beam Launched SNC: • ORP380-ORP381 I Girder Launched NCC P1: • Horamavu Station P8 1x CC Arms Completed • Veerannapalya Station P3 CC Beam Staging • Veerannapalya Station P7 L CL To TL Cast NCC P2: • DN-AP338 Formwork

BLR Metro Tracker (@blrmetrotracker) 's Twitter Profile Photo

Sheet Changelog : 21-01-2026 Afcons: • Iblur Red Station P4L Pile Excavated SNC: • ORDP2-ORDP3 Composite Girder Launched NCC P1: • HBR Station P8 CL To TL Formwork Assembled • AP29R Formwork Assembled • UP-AP328 Formwork Assembled • AP320L Being Tied • AP317R Cast •