December 2024 status report for LA Metro’s D Line Extension Section 3. 57.7% as of 12/27/24, +0.6% since 11/29/24. Additional work (contract modifications) were added to contract, decreasing progress as percentage of contract value. libraryarchives.metro.net/DPGTL/StatusRe…

December 2024 status report for LA Metro’s D Line Extension Section 3. 57.7% as of 12/27/24, +0.6% since 11/29/24. Additional work (contract modifications) were added to contract, decreasing progress as percentage of contract value.
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

December 2024 status report for LA Metro’s East San Fernando Valley (ESFV) line. Utility adjustment package 6 is almost finished. libraryarchives.metro.net/DPGTL/StatusRe…

December 2024 status report for LA Metro’s East San Fernando Valley (ESFV) line. Utility adjustment package 6 is almost finished.
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

January 2025 status report for LA Metro’s D Line Extension Section 1. 96% as of 1/31/25, +0.3% since 12/27/24. Contractor added 30 days to forecast completion, now 11/8/25 instead of 10/9/25. libraryarchives.metro.net/DPGTL/StatusRe…

January 2025 status report for LA Metro’s D Line Extension Section 1. 96% as of 1/31/25, +0.3% since 12/27/24. Contractor added 30 days to forecast completion, now 11/8/25 instead of 10/9/25. 
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

January 2025 status report on LAX Automated People Mover. 91.7% as of 1/25/25, +0% since 12/28/25. Percentages are misleading (change orders distort progress). Contractor added 2 weeks to estimated service date (now 1/12/26 instead of 12/29/25). emma.msrb.org/P21897139-P214…

January 2025 status report on LAX Automated People Mover. 91.7% as of 1/25/25, +0% since 12/28/25. Percentages are misleading (change orders distort progress). Contractor added 2 weeks to estimated service date (now 1/12/26 instead of 12/29/25).
emma.msrb.org/P21897139-P214…
numble (@numble) 's Twitter Profile Photo

January 2025 status report for LA Metro’s D Line Extension Section 2. 76.7% as of 1/31/25, +0.5% since 12/27/24. No change in forecast completion this month (around early/mid November 2026). libraryarchives.metro.net/DPGTL/StatusRe…

January 2025 status report for LA Metro’s D Line Extension Section 2. 76.7% as of 1/31/25, +0.5% since 12/27/24. No change in forecast completion this month (around early/mid November 2026). 
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

January 2025 status report for LA Metro’s D Line Extension Section 3. 59.3% as of 1/31/25, +1.5% since 12/27/24. libraryarchives.metro.net/DPGTL/StatusRe…

January 2025 status report for LA Metro’s D Line Extension Section 3. 59.3% as of 1/31/25, +1.5% since 12/27/24. 
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

January 2025 status report for LA Metro’s East San Fernando Valley (ESFV) line. They finished negotiations and started work on 6 early work packages (out of 12 total). libraryarchives.metro.net/DPGTL/StatusRe…

January 2025 status report for LA Metro’s East San Fernando Valley (ESFV) line. They finished negotiations and started work on 6 early work packages (out of 12 total).
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

February 2025 status report for LA Metro’s D Line Extension Section 1. 96.3% as of 2/28/25, +0.3% since 1/31/25. Contractor added 19 days to forecast completion, now 11/27/25 instead of 11/8/25. libraryarchives.metro.net/DPGTL/StatusRe…

February 2025 status report for LA Metro’s D Line Extension Section 1. 96.3% as of 2/28/25, +0.3% since 1/31/25. Contractor added 19 days to forecast completion, now 11/27/25 instead of 11/8/25.
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

February 2025 status report on LAX Automated People Mover. 91.7% as of 2/22/25, +0.1% since 1/25/25. Percentages are misleading (change orders distort progress). Contractor added 28 days to estimated service date, now 2/9/26 instead of 1/12/26. emma.msrb.org/P11833966-P114…

February 2025 status report on LAX Automated People Mover. 91.7% as of 2/22/25, +0.1% since 1/25/25. Percentages are misleading (change orders distort progress). Contractor added 28 days to estimated service date, now 2/9/26 instead of 1/12/26.
emma.msrb.org/P11833966-P114…
numble (@numble) 's Twitter Profile Photo

February 2025 status report for LA Metro’s D Line Extension Section 2. 73.5% as of 2/28/25, -3.2% since 1/31/25. Percentage decreased because $72m of extra work was added. Contractor added 7 days to forecast completion, now around mid/late November 2026. libraryarchives.metro.net/DPGTL/StatusRe…

February 2025 status report for LA Metro’s D Line Extension Section 2. 73.5% as of 2/28/25, -3.2% since 1/31/25. Percentage decreased because $72m of extra work was added. Contractor added 7 days to forecast completion, now around mid/late November 2026. 
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

February 2025 status report for LA Metro’s D Line Extension Section 3. 60.8% as of 2/28/25, +1.5% since 1/31/25. libraryarchives.metro.net/DPGTL/StatusRe…

February 2025 status report for LA Metro’s D Line Extension Section 3. 60.8% as of 2/28/25, +1.5% since 1/31/25. 
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

February 2025 status report for LA Metro’s East San Fernando Valley (ESFV) line. Utility adjustments package 6 is 90% done, and work has started on package 4. libraryarchives.metro.net/DPGTL/StatusRe…

February 2025 status report for LA Metro’s East San Fernando Valley (ESFV) line. Utility adjustments package 6 is 90% done, and work has started on package 4.
libraryarchives.metro.net/DPGTL/StatusRe…
numble (@numble) 's Twitter Profile Photo

April 2025 LA Metro presentation on LA River Path project. Draft EIR coming this year, with board selection of alignment in 2026. Looking at 3 options. At least 46% of path would be elevated (where owners do not make enough land available). dropbox.com/scl/fi/e7ophdf…

April 2025 LA Metro presentation on LA River Path project. Draft EIR coming this year, with board selection of alignment in 2026. Looking at 3 options. At least 46% of path would be elevated (where owners do not make enough land available).

dropbox.com/scl/fi/e7ophdf…
numble (@numble) 's Twitter Profile Photo

LA Metro’s camera-based bus lane enforcement program on two routes issued 5,500 tickets (total $1.6m in fines) in the first month, an increase from average of 570 tickets issued per month before camera-based enforcement. laist.com/news/transport…

LA Metro’s camera-based bus lane enforcement program on two routes issued 5,500 tickets (total $1.6m in fines) in the first month, an increase from average of 570 tickets issued per month before camera-based enforcement. 

laist.com/news/transport…
numble (@numble) 's Twitter Profile Photo

March 2025 LA Metro presentation on North Hollywood-Pasadena BRT. Details on alignment and adjustments to station locations. Construction expected to start late 2025/early 2026, to open for service in late 2027. dropbox.com/scl/fo/lviazha…

March 2025 LA Metro presentation on North Hollywood-Pasadena BRT. Details on alignment and adjustments to station locations. Construction expected to start late 2025/early 2026, to open for service in late 2027.

dropbox.com/scl/fo/lviazha…
numble (@numble) 's Twitter Profile Photo

March 2025 Metrolink presentation on results of schedule changes. 42.5k rides on Dodger Parade day. Off-peak ridership increased 60% while peak ridership decreased 1%. On-time performance dropped initially but is improving. Ridership is now 60% of Pre-COVID ridership.

March 2025 Metrolink presentation on results of schedule changes. 42.5k rides on Dodger Parade day. Off-peak ridership increased 60% while peak ridership decreased 1%. On-time performance dropped initially but is improving. Ridership is now 60% of Pre-COVID ridership.
numble (@numble) 's Twitter Profile Photo

March 2025 LA Metro presentation on Link Union Station to Vernon stakeholders, focused on BNSF railroad improvements to facilitate project. Many transportation benefits now proposed for Vernon (maybe in response to city’s opposition to project). linkunionstation.com

March 2025 LA Metro presentation on Link Union Station to Vernon stakeholders, focused on BNSF railroad improvements to facilitate project. Many transportation benefits now proposed for Vernon (maybe in response to city’s opposition to project). 