RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- More good progress made today, red and yellow tees now completely stripped, stumps grinded next to white tee and began removing the mound at the back of the 9th tee to level the red and yellow tees to one height. Whitemoss Eco - Innovative Golf Course Solutions. also fitted the 10th bunkers

RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee Reconstruction- Red tee now up to the same height as the yellow tee using the mound at the back of the 9th which is now completely clear. Also began widening the white tee today towards the lane ✅⛳️

2nd tee Reconstruction- Red tee now up to the same height as the yellow tee using the mound at the back of the 9th which is now completely clear. Also began widening the white tee today towards the lane ✅⛳️
RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- Today saw the start of the sleeper retaining wall going in alongside the red and yellow tees. We also made a start on relocating the irrigation heads to the side of the tees. ⛳️

2nd tee reconstruction- Today saw the start of the sleeper retaining wall going in alongside the red and yellow tees. We also made a start on relocating the irrigation heads to the side of the tees. ⛳️
RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- Drains now fully laid in the tee and stoned and already working a treat with this horrendous weather. Retaining wall also now fully complete, fingers crossed for some better weather next week 🤞✅⛳️

RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- Another week hampered by the weather but we’ve made as much progress as possible. Tee drains connected up to its outlet, yellow and red tees have had its top layer of root zone put on, irrigation nearing completion and winter tee mat plinth installed ✅⛳️

2nd tee reconstruction- Another week hampered by the weather but we’ve made as much progress as possible. Tee drains connected up to its outlet, yellow and red tees have had its top layer of root zone put on, irrigation nearing completion and winter tee mat plinth installed ✅⛳️
RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- 70mm of rain falling on us this week so far yet again delaying our progress. Attached, a video of the 3rd outlet showing the sheer volume of water. Winter tee mat installed, steps and path starting to take shape now aswell 👍🏻⛳️

RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- Everything seems to have just come together this week. Tees laser levelled by Bancroft Amenities , steps complete, new cut through complete and path finished off. Enjoy your weekend 👍🏻✅

RGCGreens (@rgcgreens) 's Twitter Profile Photo

2nd tee reconstruction- The turf arrived early this week and the lads worked swiftly to get both tees completely turfed. The back end of the week saw the new post and rail fence go up around the tee. Another productive week ✅

2nd tee reconstruction- The turf arrived early this week and the lads worked swiftly to get both tees completely turfed. The back end of the week saw the new post and rail fence go up around the tee. Another productive week ✅
England Golf (@englandgolf) 's Twitter Profile Photo

⚠️ Small actions, big impacts Working alongside experts from The R&A's Sustainable Agronomy Service, we're delighted to bring you a series of informative features on the challenges faced and how we can all help... 🤝 Golf Monthly #TheSustainabilityDrive #RespectInGolf

RGCGreens (@rgcgreens) 's Twitter Profile Photo

Apologies if anyone has had difficulty with the attached email address. The issue should now have been resolved ⛳️