Northland Drive M-57 to Indian Lakes Rd •May 5 - May 31, 2025 •Lane shifts; delays possible This project consists of cold milling the full depth of the existing three-lane asphalt surface, then placing two courses of HMA pavement with four-foot paved shoulders.

Northland Drive
M-57 to Indian Lakes Rd
•May 5 - May 31, 2025
•Lane shifts; delays possible
This project consists of cold milling the full depth of the existing three-lane asphalt surface, then placing two courses of HMA pavement with four-foot paved shoulders.
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

10 Mile Road Main St to Wolverine Blvd •May 5 - July 8, 2025 This project will be completed in phases. Intersection widening begins 5/5 •May 5: Lane Shift (May 5); delays possible •June 9: EB traffic maintained, WB traffic detoured

10 Mile Road
Main St to Wolverine Blvd
•May 5 - July 8, 2025
This project will be completed in phases.
Intersection widening begins 5/5
•May 5: Lane Shift (May 5); delays possible
•June 9: EB traffic maintained, WB traffic detoured
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Utility Project Update Eastbound 3 Mile Road Limits: Arbor Chase to Maguire Schedule (subject to change): •May 12 - May 26, 2025 •Right lane closed •Delays possible About: Permitted utility work; gas main installation

Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project Update 17 Mile Road Limits: Algoma Avenue to Pine Island Drive Schedule (subject to change): •May 13 - May 17, 2025 •Closed to through traffic •Closed to all traffic at open cut of road About: Culvert and catch basin work

Project Update
17 Mile Road
Limits: Algoma Avenue to Pine Island Drive
Schedule (subject to change):
•May 13 - May 17, 2025
•Closed to through traffic
•Closed to all traffic at open cut of road
About: Culvert and catch basin work
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project Update Bridge: Sparta No. 32 Location: Fruitridge Avenue over Nash Creek (North of 12 Mile Rd) Schedule (subject to change): •May 13 - May 19, 2025 •Closed to all traffic at the bridge •Detour posted About: Concrete beam repair

Project Update
Bridge: Sparta No. 32
Location: Fruitridge Avenue over Nash Creek (North of 12 Mile Rd)
Schedule (subject to change):
•May 13 - May 19, 2025
•Closed to all traffic at the bridge
•Detour posted
About: Concrete beam repair
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project Update Bridge: Vergennes No. 30 Flat River Drive over the Flat River between Vergennes St. & Burroughs St. •May 14 - May 21, 2025 •Closed to all traffic at the bridge •Detour posted Preventative maintenance project; application of epoxy overlay on bridge deck.

Project Update
Bridge: Vergennes No. 30
Flat River Drive over the Flat River between Vergennes St. & Burroughs St.
•May 14 - May 21, 2025
•Closed to all traffic at the bridge
•Detour posted
Preventative maintenance project; application of epoxy overlay on bridge deck.
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Happy Mother’s Day from KCRC! Today, we celebrate the women who guide with strength, patience and care, preparing us for the road ahead. To all the mothers, mentors and role models - thank you for all that you do! #MothersDay #DriveLikeMomWorksHere #thankyou

Happy Mother’s Day from KCRC!
Today, we celebrate the women who guide with strength, patience and care, preparing us for the road ahead. To all the mothers, mentors and role models - thank you for all that you do!
#MothersDay #DriveLikeMomWorksHere #thankyou
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Some severe weather could be headed our way after 9 PM. Reminder: 📞for road emergencies that restrict travel, call 911 💻for non-emergency road issues, please report here via KCRC’s online form: bit.ly/3zhOD0I

Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project Complete! The preventative maintenance of Vergennes Bridge #30 included deck patching, expansion joint replacement, water repellant treatment, and epoxy overlay of the bridge deck. Contractor: Anlaan Corporation #projectcomplete #bridges #preventativemaintenance

Project Complete! The preventative maintenance of Vergennes Bridge #30 included deck patching, expansion joint replacement, water repellant treatment, and epoxy overlay of the bridge deck. Contractor: Anlaan Corporation
#projectcomplete #bridges #preventativemaintenance
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project complete. Bridge open to traffic! KCRC performed concrete beam repair on Sparta Bridge No. 32 on Fruit Ridge Avenue over Nash Creek.

Project complete. Bridge open to traffic! KCRC performed concrete beam repair on Sparta Bridge No. 32 on Fruit Ridge Avenue over Nash Creek.
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project Update Plainfield Bridge #25 West River Drive over the Rogue River •May 29 - July 2, 2025 •Lane Closures •Two-way traffic maintained •Delays expected Preventative maintenance: substructure repair, joint gland replacement, water repellant, 7 epoxy overlay on deck

Project Update
Plainfield Bridge #25
West River Drive over the Rogue River
•May 29 - July 2, 2025
•Lane Closures
•Two-way traffic maintained
•Delays expected
Preventative maintenance: substructure repair, joint gland replacement, water repellant, 7 epoxy overlay on deck
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project Update 17 Mile Road Limits: Myers Lake Avenue to Pine Lake Avenue Schedule (subject to change): • May 27 - June 13, 2025 Traffic: • Closed to through traffic • Detour posted Existing surface will be crushed, shaped, and repaved

Project Update
17 Mile Road
Limits: Myers Lake Avenue to Pine Lake Avenue
Schedule (subject to change):
• May 27 - June 13, 2025
Traffic:
• Closed to through traffic
• Detour posted
 Existing surface will be crushed, shaped, and repaved
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Permitted Utility Work Road: Courtland Drive (Northbound) Location: Barley Drive (north of 12 Mile Road) Schedule (subject to change): • May 27 - May 30, 2025 Traffic: • Lane Closures • Two-way traffic maintained

Permitted Utility Work
Road: Courtland Drive (Northbound)
Location: Barley Drive (north of 12 Mile Road)
Schedule (subject to change):
• May 27 - May 30, 2025
Traffic:
• Lane Closures
• Two-way traffic maintained
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

BRIDGE REHABILITATION Grand Rapids #16 Crahen Ave, north of Fulton St/M-21 Over Grand Rapids Eastern RR •6/9 - 8/29/25 •Closed to all traffic at bridge •Detour posted Contractor: Milbocker and Sons, Inc. BRIDGE REHABILITATION

BRIDGE REHABILITATION
Grand Rapids #16
Crahen Ave, north of Fulton St/M-21
Over  Grand Rapids Eastern RR
•6/9 - 8/29/25
•Closed to all traffic at bridge
•Detour posted
Contractor: Milbocker and Sons, Inc.
BRIDGE REHABILITATION
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Bridge: Ada #8 Pettis Avenue, just north of Knapp Street, over Egypt Creek •6/9 - 7/2/25 •Closed to all traffic at bridge •Detour posted Superstructure repair, removing the select area of the existing concrete slab and replacing with two prestressed concrete box beams.

Bridge: Ada #8
Pettis Avenue, just north of Knapp Street, over Egypt Creek
•6/9 - 7/2/25
•Closed to all traffic at bridge
•Detour posted
Superstructure repair, removing the select area of the existing concrete slab and replacing with two prestressed concrete box beams.
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Ritchie Ave: 14 Mile Rd to 15 Mile Rd Russell St: Northland Dr to Ritchie Ave Schedule for both projects(subject to change): •June 9 - July 3, 2025 •Closed to through traffic •Detour posted Contractor: Michigan Paving & Materials About: Crush & Shape pavement replacement

Ritchie Ave: 14 Mile Rd to 15 Mile Rd
Russell St: Northland Dr to Ritchie Ave
Schedule for both projects(subject to change):
•June 9 - July 3, 2025
•Closed to through traffic
•Detour posted
Contractor: Michigan Paving & Materials
About: Crush & Shape pavement replacement
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Hall Street: Fernridge Dr to Paradise Lake Dr Paradise Lake Dr: Hall St to 800 ft. north •6/9 - 8/15/25 •Closed to through traffic •Detour posted Contractor: Kamminga and Roodvoets Permitted utility work/replacement of Ada Township sewage left station and sanitary force main.

Hall Street: Fernridge Dr to Paradise Lake Dr
Paradise Lake Dr: Hall St to 800 ft. north
•6/9 - 8/15/25
•Closed to through traffic
•Detour posted
Contractor: Kamminga and Roodvoets
Permitted utility work/replacement of Ada Township sewage left station and sanitary force main.
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project complete! Work on 28th Street between Kraft Avenue and Cascade Road included a partial-depth cold milling of the existing five-lane asphalt surface, followed by the application of two courses of HMA pavement. Contractor: Michigan Paving & Materials

Project complete! Work on 28th Street between Kraft Avenue and Cascade Road included a partial-depth cold milling of the existing five-lane asphalt surface, followed by the application of two courses of HMA pavement. Contractor: Michigan Paving & Materials
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Project complete! Sanitary sewer work was preceded by intersection widening and traffic signal work. Work concluded with resurfacing on 10 Mile Rd from Main St to Wolverine Blvd. Resurfacing Contractor: Michigan Paving and Materials

Project complete! Sanitary sewer work was preceded by intersection widening and traffic signal work. Work concluded with resurfacing on 10 Mile Rd from Main St to Wolverine Blvd.  Resurfacing Contractor: Michigan Paving and Materials
Kent County Road Commission (@mikcrc) 's Twitter Profile Photo

Permitted Work 76th Street 1200 ft east of Whistlestop Park Closed at Work Zone (*entrance to Whistlestop Park 7/8 - 8/2/25 What: Placing sanitary sewer, water main crossing, storm sewer crossing, roadway widening, and milling and paving for plat entrance.

Permitted Work
 76th Street
1200 ft east of Whistlestop Park
Closed at Work Zone (*entrance to Whistlestop Park 
7/8 - 8/2/25
What: Placing sanitary sewer, water main crossing, storm sewer crossing, roadway widening, and milling and paving for plat entrance.