Caltrans and OCTA will add one regular lane and one carpool lane in each direction of SR-55 between I-405 and I-5.

ID: 4457462779

linkhttps://linktr.ee/55fwyproject calendar_today04-12-2015 22:24:12

829 Tweet

181 Followers

72 Following

55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Coming Soon! Crews are expected to reconstruct the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. Additional information will be provided in future communications.

Coming Soon! Crews are expected to reconstruct the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. Additional information will be provided in future communications.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to pour concrete at the railroad bridge, which will require closing the northbound McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes on northbound SR-55 between these ramps. This work is expected to occur from 9 p.m., Thursday, April 9 to

Crews are expected to pour concrete at the railroad bridge, which will require closing the northbound McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes on northbound SR-55 between these ramps. This work is expected to occur from 9 p.m., Thursday, April 9 to
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to pour concrete at the Dyer Road bridge, which will require closing eastbound and westbound Dyer underneath the freeway from 9 p.m., Friday, April 10 to 5 a.m., Saturday, April 11. In addition, northbound Grand Avenue will be closed during this time. Business

Crews are expected to pour concrete at the Dyer Road bridge, which will require closing eastbound and westbound Dyer underneath the freeway from 9 p.m., Friday, April 10 to 5 a.m., Saturday, April 11. In addition, northbound Grand Avenue will be closed during this time. Business
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Spend an afternoon enjoying live music at Great Park Palm Court Arts Complex on Saturday, April 11 from 1 to 3 p.m. Guests are invited to relax with blankets or chairs and take in a vibrant mix of jazz styles in a beautiful outdoor setting. cityofirvine.org/arts-irvine/gr…

Spend an afternoon enjoying live music at Great Park Palm Court Arts Complex on Saturday, April 11 from 1 to 3 p.m. Guests are invited to relax with blankets or chairs and take in a vibrant mix of jazz styles in a beautiful outdoor setting.

cityofirvine.org/arts-irvine/gr…
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to remove falsework or temporary support structures along the east side of the SR-55 freeway bridge over the railroad. This work will require nighttime closures of the northbound McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes between

Crews are expected to remove falsework or temporary support structures along the east side of the SR-55 freeway bridge over the railroad. This work will require nighttime closures of the northbound McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes between
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to reconstruct the NB Dyer Road straight on-ramp, which will require an extended closure of the ramp. During this period, crews are also expected to perform an extended closure of the NB SR-55 outside lane between Dyer Road and Warner Avenue for paving work.

Crews are expected to reconstruct the NB Dyer Road straight on-ramp, which will require an extended closure of the ramp. During this period, crews are also expected to perform an extended closure of the NB SR-55 outside lane between Dyer Road and Warner Avenue for paving work.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Celebrate Earth Day at Catch the Rain on April 22 from 5:30 to 7 p.m. at El Salvador Park. Enjoy family-friendly activities on water conservation and native plants, plus free rain barrels and plants while supplies last. Learn more at tinyurl.com/SAcatchtherain.

Celebrate Earth Day at Catch the Rain on April 22 from 5:30 to 7 p.m. at El Salvador Park. Enjoy family-friendly activities on water conservation and native plants, plus free rain barrels and plants while supplies last. Learn more at tinyurl.com/SAcatchtherain.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews will be performing concrete paving work to reconstruct the southbound SR-55 McFadden Avenue on-ramp. This will require an extended closure of the ramp beginning at 9 p.m., Wednesday, May 6 to 5 a.m., Friday, June 5. Visit octa.net/55Construction to view real-time updates

Crews will be performing concrete paving work to reconstruct the southbound SR-55 McFadden Avenue on-ramp. This will require an extended closure of the ramp beginning at 9 p.m., Wednesday, May 6 to 5 a.m., Friday, June 5. Visit octa.net/55Construction to view real-time updates
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Reminder! Crews are expected to perform an extended closure of the northbound (NB) Dyer Road loop on-ramp, as well as the NB SR-55 outside lane between Dyer Road and Warner Avenue for paving work. The on-ramp and outside lane are expected to close as soon as 9 p.m., Friday, April

Reminder! Crews are expected to perform an extended closure of the northbound (NB) Dyer Road loop on-ramp, as well as the NB SR-55 outside lane between Dyer Road and Warner Avenue for paving work. The on-ramp and outside lane are expected to close as soon as 9 p.m., Friday, April
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to perform paving work, which will require closing the southbound I-5 to southbound SR-55 connector, as well as the southbound McFadden Avenue off-ramp from 9 p.m. to 5 a.m. nightly, Tuesday, April 28 through Friday, May 1.

Crews are expected to perform paving work, which will require closing the southbound I-5 to southbound SR-55 connector, as well as the southbound McFadden Avenue off-ramp from 9 p.m. to 5 a.m. nightly, Tuesday, April 28 through Friday, May 1.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to perform a deck pour at the railroad bridge, which will require closing the northbound McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes on northbound SR-55 between these ramps from 9 p.m., Monday, May 4 to 5 a.m., Tuesday, May 5.

Crews are expected to perform a deck pour at the railroad bridge, which will require closing the northbound McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes on northbound SR-55 between these ramps from 9 p.m., Monday, May 4 to 5 a.m., Tuesday, May 5.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Join the community in celebrating culture, connection, and tradition at the Viva Tustin Celebration on Friday, May 1 from 3 to 6 p.m. at Frontier Park. This free event brings neighbors together to honor Hispanic heritage through music, food, and community spirit. Learn more at

Join the community in celebrating culture, connection, and tradition at the Viva Tustin Celebration on Friday, May 1 from 3 to 6 p.m. at Frontier Park. This free event brings neighbors together to honor Hispanic heritage through music, food, and community spirit.

Learn more at
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Coming Soon! Crews are expected to reconstruct the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. Additional information will be provided in future communications.

Coming Soon! Crews are expected to reconstruct the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. Additional information will be provided in future communications.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to perform paving work, which will require closing the southbound I-5 to southbound SR-55 connector, as well as the southbound McFadden Avenue off-ramp from 9 p.m. to 5 a.m. nightly, Tuesday, May 5 through Friday, May 8.

Crews are expected to perform paving work, which will require closing the southbound I-5 to southbound SR-55 connector, as well as the southbound McFadden Avenue off-ramp from 9 p.m. to 5 a.m. nightly, Tuesday, May 5 through Friday, May 8.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Reminder! Crews will be performing concrete paving work to reconstruct the southbound SR-55 McFadden Avenue on-ramp. This will require an extended closure of the ramp beginning at 9 p.m., tonight, Wednesday, May 6 to 5 a.m., Friday, June 5.

Reminder! Crews will be performing concrete paving work to reconstruct the southbound SR-55 McFadden Avenue on-ramp. This will require an extended closure of the ramp beginning at 9 p.m., tonight, Wednesday, May 6 to 5 a.m., Friday, June 5.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

Crews are expected to reconstruct the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. The off-ramp is expected to close as soon as 9 p.m., Tuesday, May 12 and reopen to motorists by 9 p.m., Friday, May 22.

Crews are expected to reconstruct the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. The off-ramp is expected to close as soon as 9 p.m., Tuesday, May 12 and reopen to motorists by 9 p.m., Friday, May 22.
55 Freeway Project (@55fwyproject) 's Twitter Profile Photo

As Construction Safety Week comes to an end, it’s a reminder that small choices make a big impact. Stay alert, wear proper gear, and follow all signage. Whether driving through or working nearby, we all play a role in keeping our community safe. 🚧

As Construction Safety Week comes to an end, it’s a reminder that small choices make a big impact. Stay alert, wear proper gear, and follow all signage. Whether driving through or working nearby, we all play a role in keeping our community safe. 🚧