Executive Engineer STD-II Jammu
@stdengineer
ID: 1376091972323082244
28-03-2021 08:41:35
68 Tweet
94 Takipçi
49 Takip Edilen
Chairman Sir inspecting 11kV network in Channi Himmat.Jammu Power DISCOM Chief Engineer Distribution, JPDCL Jammu SE (O & M) Circle Jammu JPDCL
10 MVA 33/11KV power transformer secessfully charged at Raya R/Stn. as existing 8 MVA transformer got damaged on 8th Jan 22 and temporarily power was restored with a standby 5 MVA transformer resulting in heavy curtailment in the area @ShivAnantTayal Jammu Power DISCOM
Power in Satwari , Shastri Nagar, Ashok Nagar areas is Off since 9:40 am. Power will be restored shortly as soon as it is put On from Barn Grid.. Inconvenience causedid regretted @ChairmanJPDCL Power Development Department, J&K Jammu Power DISCOM @ShivAnantTayal Chief Engineer Distribution, JPDCL Jammu SE (O & M) Circle Jammu JPDCL
33 kV Canal Parladpur affecting R/Stn Parladpur and Makwal is Off . Restoration under progress and expected to be cleared in an hour as route of the 33 kV passed through Tawi river.. @ChairmanJPDCL Power Development Department, J&K Jammu Power DISCOM @ShivAnantTayal Chief Engineer Distribution, JPDCL Jammu SE (O & M) Circle Jammu JPDCL
The actual areas affected due to the shutdown of 33 kV G6 Line (at S.No1) are: Channi Himmat, Chowadi and part of Bathandi fed from 3x10 MVA Receiving Station.. @ChairmanJPDCL Power Development Department, J&K Jammu Power DISCOM @ShivAnantTayal Chief Engineer Distribution, JPDCL Jammu SE (O & M) Circle Jammu JPDCL
Due to some technical snag in 10 MVA transformer at 2x10 MVA Sidhra R/Stn. Power to Tawi Vihar and adjoining areas is affected.. The load is being shifted on standby 10 MVA transformer Restoration is expected by 11 pm @ChairmanJPDCL Jammu Power DISCOM @ShivAnantTayal
Due to damage in 33 kV line, power supply to Channi Himmat and adjoining areas is affected. Restoration under progress and expected with in 90 minutes or so.. Inconvenience caused is highly regretted @ChairmanJPDCL SE (O & M) Circle Jammu JPDCL Power Development Department, J&K @ShivAnantTayal
Due to some Technical snag in 5 MVA, 66/11 kV power transformer , power affected at R/stn Rehyian (Samba).. Restoration work is underprogress .. @ChairmanJPDCL Jammu & Kashmir Power Development Corporation Ltd. @ShivAnantTayal
To ensure smooth power supply, the Deptt. is replacing an old 10 MVA Transformer at Trikuta Ngr. R/Stn. Power supply area fed from this R/Stn. shall be affected from 8 am to 6 pm on 26th Nov 22 @ShivAnantTayal Chief Engineer Distribution, JPDCL Jammu SE (O & M) Circle Jammu JPDCL @ChairmanJPDCL Executive Engineer Electric Division-II, JPDCL Executive Engineer STD-II Jammu