📍S.R. 156 - Switzerland Co. ✅NOW OPEN✅: S.R. 156 has reopened just east of Florence near Bulgar Tapp Road following a slide correction project in Switzerland County.

📍S.R. 156 - Switzerland Co.

✅NOW OPEN✅: S.R. 156 has reopened just east of Florence near Bulgar Tapp Road following a slide correction project in Switzerland County.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

INDOT is seeking applicants for its Engineering Scholarship Program, available for undergraduate and graduate civil engineering students. Applications for the 2026-2027 school year must be emailed or postmarked by Wednesday, December 31. More: indotscholarship.in.gov

INDOT is seeking applicants for its Engineering Scholarship Program, available for undergraduate and graduate civil engineering students. Applications for the 2026-2027 school year must be emailed or postmarked by Wednesday, December 31.

More: indotscholarship.in.gov
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

On/after Wednesday, 10/22, crews will temporarily close NB U.S. 31 just north of E C.R. 300 N (Earlywood Drive) to complete pipe repair work in Franklin. The closure will take place from approximately 8 p.m. to 6 a.m. for up to one night. More: bit.ly/4hhgsIi

On/after Wednesday, 10/22, crews will temporarily close NB U.S. 31 just north of E C.R. 300 N (Earlywood Drive) to complete pipe repair work in Franklin. The closure will take place from approximately 8 p.m. to 6 a.m. for up to one night.

More: bit.ly/4hhgsIi
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍I-65 at S.R. 250 - Jackson Co. Tonight, crews will close the right lane of NB and SB I-65 at S.R. 250 in Uniontown (Exit 41) to remove temporary barrier wall. The left lanes will remain open. The lane closures will be used from approx. 9 p.m. to 5 a.m. for up to one night.

📍I-65 at S.R. 250 - Jackson Co.

Tonight, crews will close the right lane of NB and SB I-65 at S.R. 250 in Uniontown (Exit 41) to remove temporary barrier wall.  The left lanes will remain open. The lane closures will be used from approx. 9 p.m. to 5 a.m. for up to one night.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍S.R. 144 - Johnson/Morgan Co. Beginning today at approximately 9 a.m., crews will conduct daytime flagging operations on S.R. 144 over the White River just west of I-69 in Waverly. Flagging operations are expected to take up to seven hours, weather permitting.

📍S.R. 144 - Johnson/Morgan Co.

Beginning today at approximately 9 a.m., crews will conduct daytime flagging operations on S.R. 144 over the White River just west of I-69 in Waverly. Flagging operations are expected to take up to seven hours, weather permitting.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

On/after Sat, 10/25, crews will begin bridge deck overlay work on S.R. 48 over Richland Creek in Monroe Co. Temporary traffic signals will be used on S.R. 48 while work is in progress. Work is expected to be complete in late November. More: bit.ly/4qe5Tdc

On/after Sat, 10/25, crews will begin bridge deck overlay work on S.R. 48 over Richland Creek in Monroe Co. Temporary traffic signals will be used on S.R. 48 while work is in progress. Work is expected to be complete in late November.

More: bit.ly/4qe5Tdc
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

➡ Have a concern, question, or request about an INDOT roadway in your area? You can reach INDOT's customer service team by visiting INDOT4U.com or calling 855-463-6848.

➡ Have a concern, question, or request about an INDOT roadway in your area? You can reach INDOT's customer service team by visiting INDOT4U.com or calling 855-463-6848.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

💡 Why RCIs? 💡 The data tells us why. Reduced conflict intersections have been effective in the locations where they’ve been installed and are undeniably improving safety and mobility throughout the Hoosier state. Learn more ➡️ bit.ly/INDOTRCI

💡 Why RCIs? 💡

The data tells us why. Reduced conflict intersections have been effective in the locations where they’ve been installed and are undeniably improving safety and mobility throughout the Hoosier state. 

Learn more ➡️ bit.ly/INDOTRCI
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

On/after Mon, 10/27, crews will begin traffic signal improvement work at S.R. 60 and Payne Koehler Rd in Clark Co. Intermittent daytime single lane closures will be used during work. Work at this location is expected to be complete in early January. More: bit.ly/4qldXJb

On/after Mon, 10/27, crews will begin traffic signal improvement work at S.R. 60 and Payne Koehler Rd in Clark Co. Intermittent daytime single lane closures will be used during work. Work at this location is expected to be complete in early January.

More: bit.ly/4qldXJb
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍✅ S.R. 262 in Ohio Co. New week, new roadway reopening! S.R. 262 has reopened to two lanes over Arnold Creek following a bridge rehabilitation project just west of Rising Sun. Minor punch list work will take place under intermittent flagging operations.

📍✅ S.R. 262 in Ohio Co.

New week, new roadway reopening! S.R. 262 has reopened to two lanes over Arnold Creek following a bridge rehabilitation project just west of Rising Sun. Minor punch list work will take place under intermittent flagging operations.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

On/after Mon, 11/10, crews will begin slide repair work on S.R. 211 just east of Kron Lane in Harrison Co. Temporary traffic signals will be used while work is in progress. Work is expected to be complete in mid-December, weather permitting. More: bit.ly/49ndO1O

On/after Mon, 11/10, crews will begin slide repair work on S.R. 211 just east of Kron Lane in Harrison Co. Temporary traffic signals will be used while work is in progress. Work is expected to be complete in mid-December, weather permitting.

More: bit.ly/49ndO1O
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

BOO!!👻 Did we get your attention?👀➡️ Your daily drive shouldn't be giving you a fright! 😱 Let us know about issues on state roads at indot4u.com or call (855) 463-6848 to speak with a representative.

BOO!!👻

Did we get your attention?👀➡️ Your daily drive shouldn't be giving you a fright! 😱 Let us know about issues on state roads at indot4u.com or call (855) 463-6848 to speak with a representative.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍✅ U.S. 31 in Greenwood U.S. 31 has reopened to three lanes in each direction over Pleasant Run Creek following a bridge deck overlay project in Greenwood! Crews will return to complete minor punch list work at a later date.

📍✅ U.S. 31 in Greenwood

U.S. 31 has reopened to three lanes in each direction over Pleasant Run Creek following a bridge deck overlay project in Greenwood! Crews will return to complete minor punch list work at a later date.
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

If you’re stranded on a dark & foggy night, the INDOT Hoosier Helpers sponsored by GEICO, are on watch — helping keep you safe from spooky & unexpected roadside incidents. #GEICOSafetyPatrol #PedestrianSafety It’s National Pedestrian Safety Month, so be alert this #Halloween!

If you’re stranded on a dark &amp; foggy night, the INDOT Hoosier Helpers sponsored by <a href="/GEICO/">GEICO</a>, are on watch — helping keep you safe from spooky &amp; unexpected roadside incidents. #GEICOSafetyPatrol #PedestrianSafety

It’s National Pedestrian Safety Month, so be alert this #Halloween!
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

On/after Wed, 11/5, the speed limit will be reduced on S.R. 62 between Toler Rd and Morris Ave in Corydon. The speed limit will decrease from 45 mph to 35 mph between Toler Rd and S.R. 135 and from 40 mph to 35 mph between S.R. 135 and Morris Ave. More: bit.ly/4oPHrgV

On/after Wed, 11/5, the speed limit will be reduced on S.R. 62 between Toler Rd and Morris Ave in Corydon. The speed limit will decrease from 45 mph to 35 mph between Toler Rd and S.R. 135  and from 40 mph to 35 mph between S.R. 135 and Morris Ave.

More: bit.ly/4oPHrgV
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍S.R. 60 - Clark Co. Culvert repair work continues on S.R. 60 between Poindexter Ln and East St. Joe Rd southwest of Sellersburg. On/after Mon, 11/3, crews will begin using intermittent flagging operations while work is in progress. ‼️Read More: bit.ly/3JEYDXk

📍S.R. 60 - Clark Co.

Culvert repair work continues on S.R. 60 between Poindexter Ln and East St. Joe Rd southwest of Sellersburg. On/after Mon, 11/3, crews will begin using intermittent flagging operations while work is in progress.

‼️Read More: bit.ly/3JEYDXk
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

🎶They did the mash, the monster mash🎶 Don't drink and drive tonight, do the monster mash instead! Remember: Monster mash, not car crash. 👀... Now repeat it with me "monster mash, not car crash."

🎶They did the mash, the monster mash🎶

Don't drink and drive tonight, do the monster mash instead! Remember: Monster mash, not car crash.

👀... Now repeat it with me "monster mash, not car crash."
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍U.S. 31 in Franklin ✅Phase 1✅: This afternoon, U.S. 31 reopened to two lanes in each direction over Canary Ditch following Phase 1 bridge and culvert replacement work as part of the six-phase corridor improvement project in Franklin. ➡️More here: facebook.com/share/p/1BHZde…

📍U.S. 31 in Franklin

✅Phase 1✅: This afternoon, U.S. 31 reopened to two lanes in each direction over Canary Ditch following Phase 1 bridge and culvert replacement work as part of the six-phase corridor improvement project in Franklin. ➡️More here: facebook.com/share/p/1BHZde…
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

On/after Fri, 11/7, crews will close the right lanes of NB and SB I-65 over U.S. 31 as well as the SB I-65 off-ramp to SB U.S. 31 to perform bridge approach work at Exit 76 in Taylorsville. The closures are expected to take up to two days. More here: bit.ly/4oOPg6r

On/after Fri, 11/7, crews will close the right lanes of NB and SB I-65 over U.S. 31 as well as the SB I-65 off-ramp to SB U.S. 31 to perform bridge approach work at Exit 76 in Taylorsville. The closures are expected to take up to two days.

More here: bit.ly/4oOPg6r
INDOT Southeast (@indotsoutheast) 's Twitter Profile Photo

📍S.R. 135/S.R. 46 - Nashville Today, crews began sidewalk installation work at the NE corner of the S.R. 135/S.R. 46 intersection in Nashville. Intermittent flagging operations will be used. Work is expected to be complete in late December. Read more: facebook.com/share/p/1AakZ5…

📍S.R. 135/S.R. 46 - Nashville

Today, crews began sidewalk installation work at the NE corner of the S.R. 135/S.R. 46 intersection in Nashville. Intermittent flagging operations will be used. Work is expected to be complete in late December. Read more: facebook.com/share/p/1AakZ5…