The 2nd phase of an electric transmission project with Central Hudson has started.
Crews currently working on drilling 16 concrete foundations throughout an 11-mile section, including installing direct embeds using CMP which allows them to set the new poles and backfill.

The 2nd phase of an electric transmission project with @CentralHudson has started. Crews currently working on drilling 16 concrete foundations throughout an 11-mile section, including installing direct embeds using CMP which allows them to set the new poles and backfill.